NHPC's 160-MW Teesta Low Dam-IV hydroelectric project in West Bengal that is scheduled to be commissioned during the next fiscal is running behind schedule, Parliament was informed today.
"Teesta Low Dam-IV is scheduled to be commissioned during 2016-17... Teesta Low Dam-IV is running behind the schedule on account of... Reasons (like) delay in forest clearance... Cash crunch of the civil contractor (HCC)," Power and Coal Minister Piyush Goyal said in a written reply to Rajya Sabha.
Other reasons for the project running behind the schedule are agitation by local organisations and flash floods in 2007, 2009 and 2010, the minister said.
More From This Section
In a separate reply to the house, the minister said CEA in consultation wit the concerned utilities has broadly identified thermal power projects with a total installed capacity of 4,800 MW which could be considered for taking up for renovation and modernisation (R&M) based on viability.
"In additional to the the thermal generating units identified for R&M, a total capacity of 5,860 MW has been identified for retirement.. Some of which could be further considered for replacement with super critical units by concerned utilities," the minister said.