NTPC has cut average cost of generating electricity from coal by 13.6% in the last three months by slashing coal imports, saving consumers Rs 300 crore a month.
NTPC cut back on buying costlier imported coal as well as augmented domestic supplies to reduce fuel cost, chairman of the country's largest power generator A K Jha said.
"The measures taken have reduced average energy charges by 13.6% from Rs 2.06 per unit in September to Rs 1.78 in December," he said.
More From This Section
Energy charges are nothing but cost of fuel used by a power company to generate electricity. On top of this is added a fixed cost which is essentially the cost of building the system, to arrive at a final charge for buyer.
NTPC has also rationalised coal supplies by moving coal from the nearest mine to a generation station rather than sourcing the fuel from the mine the unit is tied up with. This brought down freight charges, he said.
Jha said the company this fiscal cut coal imports by 30% to 8.6 million tons from 12.3 million tons a year ago.
Also coal procured from e-auction has also been cut by 64% to 0.865 million tons. Reserve price for e-auction was 20% above the notified price as compared to 40% above notified price in 2014, helping cut costs, he said.
Average energy charges in September 2015 was Rs 2.06 per unit which was brought down to Rs 1.90 in October. This further fell by 10 paise in November and to Rs 1.78 per unit in December, he said.
"47% of NTPC's coal-based plants, having an installed capacity of 14,780 Mw, have energy charge of less than Rs 1.50 per unit. 45% plants totalling 14,190 Mw capacity have energy charges ranging between Rs 1.50 to Rs 3 per unit. The rest 8% plants (2,525 Mw) have energy charge of Rs 3 to 4 per unit," he said.
NTPC has a total installed capacity of 45,548 Mw, including 39,352 Mw through directly owned units and 6,196 Mw through subsidiaries and joint ventures. It has 18 coal fired, 7 gas based, eight solar renewable, one hydroelectric and seven subsidiaries/joint venture power stations.
Giving examples, he said the Badarpur power plant near Delhi has seen energy charges come down from Rs 4.80 to Rs 4.04 per unit. The plant is operating only one unit of 210 Mw.
NTPC has also improved coal inventories at power plants to 103 million tons from 60 million tons previously. Pit head or power stations at the mouth of a coal mine, have inventory of 15 days and non-pit head stations have 30 day inventory, he added.