Observing that the national transporter has not shown any "enthusiasm" in implementing the project, the committee has recommended that there should be in-built system of fixing responsibilities for delays, non-performance and ad-hoc decisions.
The Railway Convention Committee in its latest report has noted that the Railways mooted a proposal to set up a joint venture with the Kerala in 2007 to manufacture wagon and coaching components for railways in autocast and steel fabrication units situated at Cherthala of Allapuzha district of the state.
However, the developments thereafter shows that the railways had not shown any enthusiasm in implementing it, the 18-member panel observed in its report submitted in Parliament today.
The committee expressed displeasure at lack of seriousness on the part of the Railways which it blamed for inordinate delay in the implementation of the project.
The first pre-feasibility study report of the project done by RITES was available with railways in 2007 based on which provision of Rs 10 lakh was kept in the rail budget 2007-08 for the project, the committee noted.
The shareholder's agreement was signed between the Railways and Kerala in 2009. Thereafter, the proposal for setting up the joint venture was put on the back burner, the panel observed.
More From This Section
The 18-member committee headed by Arjun Charan Sethi said it was surprised to find that even after a lapse of five years the project is nowhere in sight.
The committee has found that the shareholder's agreement to set up a joint venture for manufacturing the components for wagons and coaches of Integrated Coach factory (ICF) design was signed in 2009 and in the same year the decision was taken to shift from ICF bogie frames to LHB bogie frames. MORE