Over 10,000 contract workers of state-owned Neyveli Lignite Corporation have begun an indefinite strike demanding regularisation of services even as NLC said it has not affected power generation and lignite production.
Power generation of the three thermal power stations was 2330 mw, NLC Chairman-cum-Managing Director B Surender Mohan today said.
The total capacity is 2490 mw.
More From This Section
All the three lignite mines at Neyveli were producing lignite as per target, he said, adding, surplus lignite has been stocked in the stocking yard for emergency needs.
AITUC Trade Union District Secretary, M Sekar, said over 10,000 contract workers have begun an indefinite strike since the last night shift to press their charter of demands, including service regularisation of contract workers.
NLC said the unions' demand that all long serving contract workmen be regularised as NLC employees immediately was contrary to the 12(3) settlements dated October 30, 2010 and June 3, 2012 entered into by the Contract Workmen Unions and also does not flow from the Supreme Court order under reference.