Realty major Unitech Ltd has been directed by the apex consumer commission to reimburse nearly Rs 14 lakh spent by a customer on rent after the flat for which he paid over Rs 1.37 crore in 2007 was not handed over to him till date.
The National Consumer Disputes Redressal Commission (NCDRC) also pulled up the real estate major and its top officials, Executive Chairman Ramesh Chandra and Managing Directors Sanjay Chandra and Ajay Chandra, saying "even after lapse of six years the flats are not ready".
"It is clear that the opposite parties (Unitech and its officials) want to have benefit of both the worlds. They have received the entire price of the apartment at the time of execution of the agreement. Even after the lapse of six years, the flats are not ready.
More From This Section
The bench said that after the period of six months is over, Unitech will have to pay Rs 25,000 for every additional month of delay in handing over possession and awarded Gurgaon resident Goyal Rs 50,000 as compensation.
The NCDRC also directed Unitech to reimburse the rent of Rs 42,500 per month from October 2010 to August 2012 (Rs 9.35 lakh) and Rs 50,000 from September 2012 to May 2013 (Rs 4.5 lakh) paid by Goyal.
The commission also directed the real estate company to pay the current rent of Rs 50,000 per month being paid by Goyal for the time it takes to hand over possession of the flat.