Business Standard

Infrastructure investors in wait-and-watch mode: BMI Research report

Frequent project delays are keeping investors edgy

Increased road construction activity sees higher bitumen sales for OMCs

Press Trust of India New Delhi
Even as the government is going all-out to attract Foreign Direct Investments (FDI) in the infrastructure space, foreign investors are adopting a wait-and-watch approach, BMI Research said in a report.

“Despite Prime Minister Narendra Modi government’s efforts to promote foreign investment in India — spearheaded by the Make in India programme — construction FDI in past three years has actually fallen despite overall increases in FDI inflows,” the report said.

BMI Research, part of the Fitch Group, further said: “We believe that this indicates lingering challenges in the country’s infrastructure industry, including poor institutional capacity and a cumbersome land acquisition process, that are causing some investors to take a wait-and-see approach.”
 

Frequent project delays are keeping investors edgy. Data from the Ministry of Statistics and Programme Implementation show that nearly 70% of current infrastructure projects are behind schedule, and more than 80% between 2005 and 2015.

It suggested that if India is able to continue improving its regulatory environment and reducing bureaucratic inefficiencies, investors will become more comfortable taking on a greater role in building the country’s infrastructure sector.

“Given India’s favourable macroeconomic conditions, urbanising population and current infrastructure deficit, the potential gains for both investors and the country are tremendous,” the report noted.

As many as 273 infrastructure projects, including those delayed due to land acquisition, forest clearances and other reasons, have led to a cost overrun of Rs 1.77 lakh crore.

In August 2016, the Ministry of Statistics and Programme Implementation monitored 1,167 infrastructure projects, each worth Rs 150 crore or more, across sectors such as power, railway and roads.

The ministry said in its flash report that out of the 1,167 projects, 282 are on schedule, 337 are delayed, 273 projects reported cost overrun and 85 projects saw both time and cost overrun with respect to their original project implementation schedule.

As per the report, reasons for time overruns as reported by various project implementing agencies are delays in land acquisition, forest clearance and supply of equipment.
 
Other factors responsible for such delays are fund constraints, geological surprises, problems in equipment installation, geo-mining conditions, slow progress in civil works, shortage of labour, inadequate mobilisation by contractor, Maoist problems, court cases, contractual issues, Right of Use (RoU)/Right of Way (RoW) problems, law and order situation and the like.
 
Speedy implementation of projects assumes significance in view of the government’s push to move towards high growth trajectory of over 8% and touch a double-digit mark in a few years.

Don't miss the most important news and views of the day. Get them on our Telegram channel

First Published: Dec 04 2016 | 11:33 PM IST

Explore News