Bharat Sanchar Nigam's (BSNL) ambitious $500 million digital wireless network rollout in eastern and western zones has been hit following a delay in the deployment of equipment and infrastructure by Nortel Network.
|
|
The telecom behemoth is unable to offer its services on the network that has a capacity of 7 million subscribers, even as the global communications solutions provider has overshot its mid-2005 deadline.
|
|
This is the second instance of a global company hampering BSNL's rollout plans, the earlier being IBM, which was "partly" responsible for the extension of its National Internet Backbone phase-II (NIB-II) project.
|
|
A source at BSNL said, "There is a delay on the part of Nortel and this is hampering BSNL's digital wireless network rollout in the two zones, with the company not being able to activate even one-third of the total 7 million subscriber capacity."
|
|
A majority of base transceiver stations (BTS) and other infrastructure required for the network, such as routers and switches among others, are yet to be installed, the source said.
|
|
BSNL had awarded the contract estimated at around $500 million to expand its GSM/GPRS digital wireless network in the east and south zones of India.
|
|
Under the project, which was to be completed by mid-2005, BSNL was to provide wireless services in West Bengal, Orissa, Bihar and Jharkhand (East zone) and Kerala, Karnataka, Tamil Nadu and Andhra Pradesh (south zone).
|
|
Nortel was to deploy a global system for mobile communications (GSM) and general packet radio service (GPRS) solution such as radio base stations, mobile switching centres (MSCs), intelligent networks (IN) and other related equipment.
|
|
This was to be used to provide wireless voice and data services with carrier-grade network reliability and involved setting up of over 11,000 cell sites, one of the largest in the world.
|
|
Nortel Networks vice-president Rajan Mehta confirmed that the project had overshot the deadline, but added that it was expected to be completed in the next couple of months.
|
|
"This is huge project, involving setting up of around 11,000 cell stations within 9 to 12 months. The enormity of the project can be gauged from the fact that it took over four years (1999 to 2003) for a similar number of base stations (11,000) to come up in the country," he said.
|
|
However, he also said that the services have been launched in major parts of all the four states in the south and three in the east.
|
|
Earlier, certain equipment related issues had resulted in the postponement of BSNL's NIB-II project that was to put India on par with advanced nations.
|
|
ON HOLD
|
|
BSNL was planning $500 million digital wireless network in eastern and western zones
Equipment provider, Nortel Networks has already overshot its mid-2005 deadline |
|
|
|