Argex equipment procurement process for Valleyfield plant
Vendors have commenced preliminary engineering for the longest lead items
BS B2B Bureau B2B Connect | Montreal, Quebec (Canada)

ALSO READ: Coatings industry paints big picture with pick up in rural demand
He added, “Furthermore, other equipment items that we had previously identified as having some of the longest lead times have been recategorised based on updated vendor information. The ongoing testing work that we have been carrying-out with many of the equipment vendors have led to their improved understanding of our requirements and this has led to materially reduced delivery times. In some cases, weaker market conditions for required equipment have also improved the delivery times and prices previously expected.”