However, the water crisis has not hit operations at BSP yet
The commercial production of R350 HT rails started at the universal rail mill in October last year after successful trials and clearance from the research wings of SAIL and the Railways
Bhilai Steel Plant (BSP) has decided to install solar power generation systems on the rooftops of various buildings in its plant premises and township in Bhilai. The flagship unit of the country's largest steel maker Steel Authority of India Limited (SAIL), BSP, has recently signed a memorandum of understanding with the Chhattisgarh State Renewable Energy Development Agency (CREDA) for the solar power generation project within the unit's premises, a statement issued by the plant management said on Wednesday. The proposed plan shall generate about 2 MW of electricity, it said. Besides, a project of rooftop solar energy systems installation on residences and offices in the township is also underway, which has the potential to generate about 3 MW of electricity, it said. Upon completion, the two projects shall lead to a reduction in as much as 2,900 tonnes of Carbon Dioxide emission every year, thereby helping in environment conservation, it said. On May 9 this year, a Power Purchase
The first solar project of NSPCL will open avenues of green energy portfolio for NSPCL while helping SAIL in green steel production
The total volume of steel supplied by SAIL for the project is 24,216 tonnes
BSP's Steel Melting Shop 2 produces cast blooms from its bloom casters. The blooms are then rolled into rails at Rail and Structural Mill
They include TMT bars in 550D grade in 12 mm diameter produced in Bar and Rod Mill and TMT bars in the same grade in 32 mm diameter produced in Merchant Mill, they said
Agreement is for multiple solutions like converting emissions to value-added products and fuel
The Sabarmati facility is expected to produce 100,000 tonnes of 260-meter welded panels annually
For developing the new product, steel melting shop III produced the required heat with rich chemistry of carbon and manganese, the spokesperson said
This will lead to an investment of Rs 6,000 crore in the form of equipment from Ramcharan
The EVs will be replacing petrol-driven vehicles
The High Carbon IS 7904 HC38 & HC 80 grade steel wire rod is high value-added steel developed through SMS 3 - WRM route
The company is also executing export orders for an additional volume of around 10,000 tonnes of plates, which is likely to be completed in February
Besides Bharat Heavy Electricals (BHEL), the Indian Railways and two private infrastructure companies had placed bulk orders
A stranded ferry from the Visakhapatnam port is cited to be the reason for plunging it into a deep crisis.
The 508-km project, scheduled for completion in October 2028, will connect Mumbai and Ahmedabad with a high-speed rail track where trains will travel at a speed of 320 kms per hour
State-owned firm neither applied technical due diligence nor did techno-commercial study to assess viability before allotment of its two captive coal blocks, says report
There is threat to its iron ore security in Maoist-affected Bastar district of Chhattisgarh
The minister said this while interacting with officials of SAIL's Bhilai Steel Plant (BSP) in Bhilai, Chhattisgarh, the PSU said in a statement